Diggers Beach Reserve Upgrade

diggers 6
Diggers Beach Reserve Upgrade – SPS, Ablutions & Storage building
Client Coffs Harbour City Council
Contract (26 weeks)
  • Construction of  Sewage pumping station and sewer rising main
  • Construction of new Ablutions and storage building
  • Decommissioning and demolition of the old ablutions block

 

Value $ 0.700 M
Scope The Diggers Beach Reserve Upgrade project involved the construction of a new ablutions building including a storage section, a sewer pumping station and sewer rising main to existing sewerage reticulation system, and decommissioning & demolition of the old ablutions building.The scope of work included:

  • Construction of architecturally designed ablutions building with attached storage area for life saving water craft.
  • Construction of a compact sewage pumping station and 180m long DN63 Polyethylene Sewer rising main in an existing manhole in the gravity reticulation system.
  • Demolition of the old redundant ablutions block on opposite side of beach entrance road.

 

Project Status Completed

 

 

diggers 6 diggers 7 diggers 2 diggers 1 diggers 5 diggers 3 diggers 4